Construction of a Combined Heat and Power (CHP) station
Client: METKA S.A.
Construction Period: 2006-2007
Facilities: Aluminium of Greece S.A. in Aghios Nikolaos Paralia Distomou, Viotia
Subject of contract:
- Works on the two main Boilers of the CHP Unit.
- Erection works of the main pipe rack, the auxiliary pipe rack, and the steam extraction pipe rack.
- Execution of the erection of the Natural Gas receiving station.
- Erection works of the auxiliary dual-fuel Boiler of the CHP Unit.
- Erection works for a section of the plastic (GRP) pipes, fittings, valves for special pipe sections, instruments, and supports for the open-sea water cooling circuit of the CHP Unit.
- Erection works of Steel Structures and Mezzanines within the Steam Turbine building of the CHP Units.