Construction of a gas turbine power plant, combined cycle, electricity production, nominal power 435MWE | Thiva, Viotia
Client: TERNA S.A.
Subject of contract:
- Execution of erection works for the steam turbine and the generator of the HERON II combined cycle unit.
- Execution of prefabrication and erection works for the oil system of the gas turbine – steam turbine and generator of the HERON II combined cycle unit.
- Assembly of generator – turbine and pipes.