Procurement and Installation of the Boiler (330 MW) along with Auxiliary Installations for the Under-construction 1st Unit of the Ahlada Power Station


Client: METKA S.A.

Subject of contract: 

  • Erection of the pylon and the hangers for the pressure parts of the boiler with a total weight of 3,295 tons.
  • Erection of the auxiliary frame of the boiler with a total weight of 4,990 tons.
  • Preparation, erection, assembly, welding of the steel parts, tightening of bolts, checks for flatness/verticality of building No. 2.
  • Preparation, erection, assembly, and welding of pipes with a total weight (8 pipes) + total weight of 944.5 tons.