Construction of the 5th unit of Ag. Demetriou
Client: METKA S.A.
Construction Period: 1994-1996
Subject of contract:
- Erection of 2,300 tons of the pylon and 100 tons of hangers.
- Erection of 2,200 tons of auxiliary frame.
- Pre-assembly and erection of a flue gas duct section from the boiler roof to the filter inlet, weighing approximately 602 tons.
- Assembly of air preheaters (LUVO).
- Assembly of part of the Detusting & Vacuum system.