Steam Power Plant of Ptolemaida – Study, procurement, transport, installation and commissioning of steam power unit V
Client: TERNA S.A.
Construction Period: 2017-2019
2017:
- Installation of inserts for the erection of construction cranes & auxiliary installation of inserts in the project foundations.
- Erection of the BURNOUT GRADE steel structure on the Boiler.
- Pre-assembly & erection works for the flue gas duct.
2018:
- Erection of the main steel structure of the Boiler.
- Hot flue gas ducts to air preheater (LUVO), hot flue gas ducts from LUBECO, cold air intake ducts, hot air ducts from LUVO to boiler, air ducts to lignite burners, hot air ducts to oil burners, hot air ducts to mills, hot air ducts to ash hopper, O.F.A. hot air ducts, cold flue gas recirculation ducts, hot flue gas recirculation ducts to mills.
- Erection of ESP filters.
2019:
- Installation of BURNERS & PIPING SPOOLS equipment in temporary erection positions.
- Erection of piping/supports & installation of pumps for the peripheral BoP systems (PIPE –RACKS).
- Assembly (mounting-welding) of the prefabricated sections of the "DISTRIBUTION POINT TO LUVO" duct.
- Installation of the underground pipeline for the auxiliary cooling water system.